A division of the Town’s Public Services Department, the Engineering Division, is committed to serving the community by supporting town departments with design and implementation of capital improvement projects including new sidewalks, paving projects, water and sewer lines, and Town facilities. To see a list of 2016 streets being resurfaced, click HERE.

Below is a list of current Town projects:

West Wilson & West McLelland Improvement Projects October 2016


Transportation GO Bond Projects Update August 2016

Transportation GO Bond Projects Schedule August 2016


Transportation GO Bond Projects Map October 2016
 
Patterson-Bell Area Improvements (2014 GO Bond)

  • Construction is underway and scheduled for Completion Fall 2016
  • New curb, sidewalk and storm drain on various streets in the Patterson-Bell area.
  • Contracted Construction Cost: $2,437,658.47
  • Patterson Avenue Overview

Main Street/Statesville Avenue (General/Powell Bill)

  • Status: Right-of-Way Phase
  • Realignment of existing intersection for improved traffic flow with new left turn lanes on the north bound and south bound legs of the intersection.
  • Construction scheduled to begin Summer 2016 and expected to last four months.
  • Estimated Cost: $325,000
  • Main Street/Statesville Avenue Concept Plan

Mill Village Sidewalk & Utilities (2014 GO Bond)

  • Status: Under Design
  • Construction in phases 2016 through 2018.
  • New sidewalk ( one side of the street) and curb & gutter to promote pedestrian walkability and also connectivity to the Downtown area.
  • Estimated Cost: $3,242,675
  • Replace Aging or undersized water and sewer lines.
  • Construction in phases from Spring 2016 to 2018.
  • Estimated Utility Fund Cost: $3,855,000
  • Mill Village Sidewalk Concept Plan
Mooresville School Network Sidewalk (2014 GO Bond)

  • Status: Right-of-Way Phase
  • New Sidewalk connecting Mooresville Middle School and Kistler Farm Road communities with Bellingham Park and Fieldstone/Magnolia Sidewalk Network.
  • Construction is expected to start Summer/Fall 2016 and last 10 months.
  • Estimated Cost: $1,456,500
  • Committed CMAQ Funding: $343,000
  • Requested Additional CMAQ Funding: $801,996
  • Total Bonded Cost: $654,504
  • Mooresville School Network Sidewalk Concept Plan
NC 115/Faith Road Intersection Improvements (2014 GO Bond)

  • Status: Preparing for right-of-way and utility coordination phase.
  • Realignment of existing intersection for improved traffic flow along with new left turn lanes on all legs of the intersection.
  • Construction is expected to start Spring 2017 and last 12 months.
  • Estimated Cost: $3,474,720
  • Committed CMAQ Funding: $1,133,625
  • Request to be made for supplemental Federal funding.
  • Developer's Portion: $253,000
  • Total Bonded Cost: $2,088,095
  • NC 115/Faith Road Concept Plan
NC 150/NC 115 Intersection Improvements (2014 GO Bond)

  • Status: Right-of-Way Phase
  • New right turn lanes on the west bound and south bound legs of the intersection.
  • Construction is expected to start Winter 2016 and last 12 months.
  • Estimated Project Cost: $1,953,283
  • Committed CMAQ Funding: $1,398,782
  • Total Bonded Cost: $554,501
  • NC 150/NC 115 Concept Plan
NC 150/NC 801 Intersection Improvements (2014 GO Bond)

  • Status: Final NCDOT review before right-of-way authorization.
  • New left lanes on all legs of the intersection.
  • Construction is expected to begin Spring/Summer 2017 and last nine months.
  • Estimated Project Cost: $2,249,800
  • Committed Bonus Allocation and CMAQ Funding: $1,719,976
  • Total Bonded Cost: $529,524
  • NC 150/NC 801 Concept Plan

Williamson Road Widening

(2014 GO Bond)

  • Coordinating with NCDOT to expedite full widening of section between Brawley School Road and NC 150. This reduces the construction duration and eliminates costs to the Town.

New Raw Water Line

(Utility Fund)

  • Status: Under Design
  • New 36" raw waterline from intake to Water Treatment Plant.
  • First phase of construction to begin in fall 2016.
  • Estimated Cost: $3.5 Million
  • Williamson Road Concept Plan
West McLelland Avenue Improvements

  • Status: Under Design
  • Complete road reconstruction including sidewalk along West McLelland from Plaza Drive to Broad Street.
  • Construction to start Fall 2017.
  • Estimated Cost: $3,60,198.75

West Wilson Avenue Improvements

  • Status: Under Design
  • New curb and pedestrian path including pedestrian bridge along West Wilson Avenue from NC 21 to Broad Street.
  • Construction to start Fall 2018.
  • Estimated Cost: $1,062,410.25